FR EN
Support Xterra-One
Xterra reference Compliance & interconnection
i
7 steps before a Hydro-Québec-compliant installation Xterra separates component compatibility from project compliance. For grid-connected self-generation, the exact bill of materials, diagram, installed equipment, tests and the master electrician's report must remain consistent through final authorization. Quebec · Hydro-Québec · CMEQ · RBQ Full reference →
View reference →

XTERRA-ONE TECHNICAL REFERENCE

Recommendations backed by a clear reference hierarchy.

Xterra-One separates Quebec requirements, professional good practice and manufacturer-specific limits. This evolving framework supports the calculator, configurator and guides.

References verified · October 19, 2026

INTERPRETING A RULE

Three levels, never mixed.

A training framework or good practice does not replace a local requirement. And a general requirement never replaces the published limits of the product actually installed.

Quebec — applicable requirement

Hydro-Québec, Quebec regulations, RBQ, CMEQ and applicable official documents take precedence when a regulatory or interconnection requirement exists.

Professional good practice

NABCEP JTAs provide a framework for design, installation, commissioning and maintenance. They structure the method without replacing Quebec requirements.

Manufacturer — equipment limit

Datasheets, installation manuals, MPPT windows, voltage and current limits, torque values and manufacturer compatibility requirements remain mandatory for the selected product.

Order of priority: when an official Quebec requirement applies, it takes precedence. NABCEP is used to structure design, installation, commissioning and maintenance. Manufacturer limits then remain mandatory for the selected product.

Some NABCEP resources refer to the NEC, OSHA or U.S. practices. They are used only as a professional framework and never replace the code applicable in Quebec, Hydro-Québec, RBQ, CMEQ or manufacturer instructions.

REFERENCE POINTS USED IN RECOMMENDATIONS

Checks required before concluding that components are compatible.

Professional good practice Manufacturer data required

MPPT controller

Controller current rating alone is not enough. Maximum cold PV voltage, MPPT window, battery voltage, allowable PV power and protection must all be compatible together.

Quebec — applicable requirement Manufacturer data required

Protection and disconnecting

Overcurrent devices, disconnects, enclosures, surge protection and shutdown functions must be sized from the actual circuit. A final rating cannot be established without the current, conductors and complete architecture.

Professional good practice Manufacturer data required

Batteries and storage

Capacity in kWh or Ah is only one criterion. Voltage, charge/discharge current, BMS, temperature, location, clearances, ventilation and inverter compatibility must also be considered.

Manufacturer — equipment limit Manufacturer data required

Connectors, terminals and distribution

Connectors and terminals must be listed for their intended use, compatible with the conductor and current, and installed according to manufacturer instructions. A mechanically possible connection is not automatically an acceptable connection.

Quebec — applicable requirement Manufacturer data required

Backup and grid isolation

A battery alone does not create a backup system. The architecture must include grid isolation, transfer, supported loads, protection and the power limits of the selected equipment. For work covered by Rénoclimat, connection of the source to the transfer switch and then to the panel must also meet program criteria and be performed by the required master electrician.

Quebec — applicable requirement

Rénoclimat 2026 — fixed battery and backup interconnection

Since October 1, 2026, Rénoclimat provides up to $4,000 for an eligible fixed battery and up to $1,000 for certain electrical work connecting a backup source. For fixed batteries, the system must notably be permanent, provide at least 5 kWh, use a true-sine-wave inverter rated at least 1.2 kW continuous and 2.5 kW surge, be able to operate with the utility grid and comply with E.12-07. Portable batteries and electric vehicles are excluded. The public-assistance stacking covered by the guide is not permitted, so Xterra displays this assistance separately and does not automatically add it to LogisVert.

Quebec — applicable requirement Manufacturer data required

7 steps before a Hydro-Québec-compliant installation

Xterra separates component compatibility from project compliance. For grid-connected self-generation, the exact bill of materials, diagram, installed equipment, tests and the master electrician's report must remain consistent through final authorization.

  1. Size the project and lock the architecture: consumption, PV capacity, grid, storage and backup.
  2. Identify the exact bill of materials: manufacturers, models, ratings, certifications and equipment characteristics to be submitted.
  3. Prepare the Hydro-Québec application and single-line diagram; an Xterra recommendation is not an interconnection approval.
  4. Wait for conditional acceptance and install according to the accepted file with the qualified electrical contractor.
  5. Verify on site the disconnecting means, labeling, neutral, grounding and consistency between the installation, diagram and bill of materials.
  6. Perform the applicable E.12-07 tests and have the master electrician complete/sign the verification report with the required supporting material.
  7. Submit the report and wait for Hydro-Québec final authorization before grid connection and commissioning.
Quebec — applicable requirement

Net metering and energy sizing

Sizing should start from actual consumption and project goals. Option I records surplus from eligible renewable generation in a kWh bank; the bank is reset according to the current official cycle, presently every 24 months. For Xterra Quebec, battery or vehicle storage is treated as local storage/backup and is not counted as an exportable self-generation source; V2H/V2X is recommended only for backup or off-grid use.

CONTINUOUS IMPROVEMENT

The reference framework is living.

The framework evolves with new standards, Hydro-Québec revisions, manufacturer documents and professional guides. Any affected rule can be updated with a new verification date.